Know what is below before you break ground.  

 

Dial before you digHitting an underground cable can cause fatal injuries, immediate loss of power to your community, and significant financial penalties. In South Australia, underground cables can be anywhere, on the footpath, under the road, or running through private property. 

You have a legal duty of care to locate these assets before you start any excavation work.  

Whether you are fencing, planting trees, or managing a large construction site, you must have a plan. 


The "Before You Dig" Process 

Don't rely on guesswork. Follow these five steps to ensure you excavate safely. 

1. Plan (Lodge your enquiry) 

At least one business day before you start, lodge a free enquiry with Before You Dig Australia (BYDA). This is the essential first step for any project. 

  • Action: Visit www.byda.com.au to request plans or download the new byda App 
     

2. Prepare (Review the documents) 

Once you receive the plans from SA Power Networks and other utilities, review them carefully. 

  • Warning: These plans are an indication only. They show the presence of cables, but may not show the exact location or depth. 
  • Look for clues: Walk the site and look for visual indicators like Stobie poles, green domes (pillars), pits, and marker posts that suggest where cables run. 
     

3. Pothole (Find the exact location) 

You must physically locate the asset before using heavy machinery. This is known as "potholing"6. 

  • Method: Use hand tools or vacuum excavation (non-destructive digging) to expose the cable.Do not use mechanical excavators or sharp power tools until you have visually confirmed where the cable is. 
     

4. Protect (Mark the asset) 

Once you expose the infrastructure, protect it. 

  • Communication: Clearly mark the location so other workers or contractors on site know exactly where it is. 
  • Support: If you are digging a trench across a cable, ensure the exposed cable is supported and not left hanging, which can damage the internal wires. 
     

5. Proceed (Excavate with care) 

Only when you have completed the steps above should you proceed with your main excavation work. 

The FREE Before You Dig Australia app is an important tool to safely plan work 

The use of the app may help minimise contact and reduce the risk of injury or death from electrocution and damage to equipment and the electricity network.

Visit: www.byda.com.au

Visit the Apple App store or Google Play store on your mobile device and search for BYDA.

Apple App store logoGoogle Play Store logo

Working Near Stobie Poles (Underground Risks) 

In South Australia, Stobie poles are not just overhead hazards. They often have cables running down the side of the pole and entering the ground. 

  • Earthing Systems: Many Stobie poles have metal "earthing mats" or rods buried in the ground surrounding the base. Hitting these can destroy the pole’s safety protection. 
  • Stability: Digging too close to a Stobie pole can make it unstable. If you need to excavate deeply within 3 metres of a pole, you must contact SA Power Networks first to check stability requirements. 

 

A Quick Note on Overhead Lines: "Look Up and Live" 

LUAL app screen on mobileWhile underground assets are hidden, overhead lines are visible—but just as dangerous. 

  • The 3-Metre Rule: Keep all people and machinery at least 3 metres away from powerlines. 
  • Use a Spotter: If you are operating machinery (like a tip truck, crane, or excavator) near lines, you must assign a dedicated spotter to guide the operator. 
  • Tiger Tails: Remember that "Tiger Tails" (yellow markers) are for visibility only—they do not insulate the wires. 

Visit the Apple App Store or Google Play store on your mobile device and search for Look up and Live.

 Google play app download    Apple app store download  


Frequently asked questions

Plans are a guide only. They indicate that assets are in the area, but they do not provide the exact millimetre-perfect location. Assets may shift over time due to soil movement or previous roadworks. You must always use "potholing" (hand digging) to verify the exact position. 

Never assume the depth. While standards exist, ground levels change over time due to landscaping, erosion, or road resurfacing. A cable could be 600mm deep, or it could be just 300mm below the surface. Always dig with caution. 

Even minor digging can potentially damage underground power and other infrastructure. 

If you’re installing a fence or mailbox, laying a driveway, doing some landscaping or having a pool installed, you need to use Before You Dig Australia to ensure you can excavate safely.  

Plans come from SA Power Networks and other asset owners and will usually be available within minutes of making a request. However, in some cases it can take up to two business days.  

In some cases, SA Power Networks (or other asset providers) may advise you to engage an accredited locator to locate underground power infrastructure. You may also opt to do this if you feel you require assistance.  


Helpful links

Visit the Before You Dig Australia website and SA WHS laws for more information about working safely near underground assets.  

Downland SA Code of Practice: Excavation Work to keep you and the people you work with safe and informed on the code of practice for excavation work.